gATP Gurus,
Please take a look the following scenario....
1. Our customers require the materials to be delivered on a specific date(not before and not after)and we always do tha without issues.
2. For example we have stock of a material which is promised for 14 days from today and no more stock is available now.
3. Now we get a sale order asking for the same material 5 days from today. But the existing stock is with the sale order 14 days from today. The thing is we can produce the material in 7 days.
What we want to is this:
We want the systen to give the stock to the new sale order and create a manufacturing order with the CTP functionality which will service the 14 day sale order.
We know CTP generally will take care by creating a planned order for a sale order. But can we achieve our requirement seamlessly is the question I am pondering over.
Any help will be highly appreciate.
Thanks,
Subash